WisDOT seeking comments on Pierce County culvert work

Proposed projects repair or replace culverts on US 10 and WIS 65

Posted 4/20/23

The Wisconsin Department of Transportation (WisDOT) is holding a virtual public involvement on proposed culvert projects on US Highway 10 and State Highway 65 in Pierce County.

Materials:  …

This item is available in full to subscribers.

Please log in to continue

Log in

WisDOT seeking comments on Pierce County culvert work

Proposed projects repair or replace culverts on US 10 and WIS 65

Posted

The Wisconsin Department of Transportation (WisDOT) is holding a virtual public involvement on proposed culvert projects on US Highway 10 and State Highway 65 in Pierce County.

Materials: https://wisconsindot.gov/Pages/projects/by-region/nw/us10wis65/default.aspx

Comments: Provide by April 28, 2023, by:

  • Email: sturgis@dot.wi.gov
  • Mail: Wisconsin Department of Transportation
    718 W. Clairemont Ave.
             Eau Claire, WI 54701
    : Adam Sturgis

The culverts are showing signs of deterioration. To address this, WisDOT is proposing the following work:

  • On culverts C-47-236 and C-47-242 on US Highway 10 between Ellsworth and Durand:
    • Replacing the wing walls on the north end of C-47-236 and replacing the guardrail.
    • Replacing C-47-242, reconstructing the roadway and removing and replacing guardrail.
  • On culverts C-47-2 and C-47-5 on State Highway 65 between Ellsworth and River Falls:
    • Replacing C-47-2, reconstructing the roadway and removing guardrail.
    • Replacing C-47-5, reconstructing the roadway and removing guardrail.

During construction on US Highway 10, motorists will encounter a shoulder closure for work on culvert C-47-236 and single-lane closures controlled by temporary traffic signals for the replacement of C-47-242. During construction, State Highway 65 will be closed to through traffic for the replacement of both culverts, and traffic will be detoured via US Highway 10, US Highway 63, State Highway 29 and State Highway 35. Work on C-47-2 and C-47-5 is anticipated to be done simultaneously, and access to residences and businesses in the project limits will be maintained.

Construction currently is scheduled to be completed in 2025.

Submitted by WisDOT 

road work, culverts, US 10, STH 65, Pierce County, Wisconsin